Construction Updates & Photos
May 21, 2026
The past two weeks have been filled with major site preparation work as construction on The Gathering Place continues to move forward steadily. Crews have been focused on excavation and preparing the foundation pad through the installation and compaction of structural fill. We are pleased to report that the site work contractor has completed the foundation sub-grade fill and compaction work, and the project successfully passed all compaction testing performed by the geotechnical engineer.
For the remainder of this week and into next week, crews will be laying out and excavating for the building footings, plumbing lines, and electrical lines. Looking ahead, work will continue on forming the foundation perimeter and beginning installation of plumbing lines, electrical conduit, the vapor barrier, and reinforcing rebar for the foundation slab. Each week brings visible progress, and it is exciting to see this long-awaited project beginning to rise from the ground. Please feel free to reach out with any questions.
Mahalo,
Alex Woodbury





